Planning of Solar Photovoltaic (PV) generation and Battery Energy Storage System (BESS) installation in a meshed transmission network involves considering investment cost, transmission losses, and voltage stability. Most of the studies on the integration of PV generation and compensation devices are based on distribution networks, but integration of PV and BESS in transmission networks through a voltage stability indicator like the L-index has not received much consideration. In this research, the Hybrid Grey Wolf-Atan-Sinc Optimization Algorithm (Hybrid GWO-ASOA) is developed and compared with the Grey Wolf Optimizer (GWO), Atan-Sinc Optimization Algorithm (ASOA), and Political Optimizer (PO) for PV and BESS installation in the IEEE 14-bus transmission network. The evaluation of candidate solutions is done with the help of the AC Newton-Raphson load flow solution, while optimization is based on minimizing the normalized weighted sum of system cost and maximum Lindex. In the case of the single peak-load formulation, the GWO and the Hybrid GWO-ASOA find 13.40 MW of PV installed at bus 14 without any BESS, with a combination fitness of 0.9227, 11.89 MW of active power losses, and an Lindex of 0.0593. In the case of the ASOA approach, 16.25 MW of PV installed at bus 14 and 5.87 MW of BESS at bus 10 reduce the losses to 10.9989 MW with an L-index of 0.0532. However, the annual cost is higher, and the combined fitness value increases to 0.9391. The hybrid algorithm takes about 10.14 seconds, compared to 46.17 seconds taken by PO, but the final output is similar to that of GWO. For 24-hour analysis, it can be seen that PV helps in reducing total loss, whereas BESS provides peak-period support for about 2% solar availability. Based on the cost coefficient, the annual cost increases for all configurations. The result will give network planners a practical basis for prioritizing PV/BESS siting and sizing decisions on meshed transmission networks.